...
Download Technical Specs PDF

How to Size BESS Backup for Cold Storage Refrigeration Loads

A cold storage warehouse should not size its BESS from total compressor nameplate power.

The correct design begins with product-temperature limits, measured room holdover time, critical refrigeration loads, compressor starting demand and the required electrical backup duration.

MegSolid evaluates cold storage projects by separating two ratings:

A BESS may support controls, evaporator fans, refrigerant pumps and selected compressors. It does not always need to operate every compressor, defrost heater and auxiliary load during an outage.

Request a Preliminary Cold Storage BESS Assessment

Submit the following data:

The preliminary review can return:

Is BESS the Right Backup Solution?

BESS is strongest when the refrigeration load can be divided into critical and deferrable groups.

Project ConditionBESS SuitabilityRecommended Direction
Generator requires 30 seconds to 10 minutes to accept loadHighUse BESS as a bridge
Frequent short grid outagesHighBattery-led critical backup
Critical refrigeration load can be reducedHighTiered-load BESS
Full refrigeration plant must run for 8–12 hoursLow as standaloneGenerator or hybrid system
Existing generator is reliable but slowHighBESS plus generator
Thermal storage is already installedHighCoordinate electrical and thermal storage
Compressor starting exceeds PCS kVAConfiguration unsuitableAdd VFD, soft starter or larger PCS
No verified temperature limits or holdover dataInsufficient informationComplete thermal assessment first

The selected energy storage system should protect the refrigeration process without unnecessarily backing up the entire facility.

The Cold Storage BESS Four-Layer Sizing Method

MegSolid does not size cold storage BESS from compressor kW alone.

The project is evaluated through four engineering layers.

Sizing LayerEngineering QuestionRequired Output
Thermal riskHow long can each room remain within its temperature limit?Maximum permitted outage duration
Critical loadWhich controls, fans, pumps and compressors must operate?Critical operating power
Transient powerWhat is the highest compressor starting demand?Required PCS kW and kVA
Energy durationHow long must the selected loads operate?Required usable and nominal kWh

This method prevents two common procurement errors:

Classify Refrigeration Loads Before Calculating Battery Capacity

Cold storage loads should be divided by operational priority.

Load TierTypical EquipmentBackup Strategy
Tier 1: Continuous controlPLCs, sensors, alarms, communications and control panelsMaintain continuously
Tier 2: Critical refrigerationEvaporator fans, refrigerant pumps and selected compressorsSupport according to temperature risk
Tier 3: Deferrable loadNoncritical compressors, defrost heaters, lighting and auxiliariesShed or restore later

The final classification depends on the stored product.

Frozen meat, pharmaceuticals, fresh produce and chilled dairy products have different temperature and recovery requirements.

USDA uses 40°F or below as a general refrigerated-food reference and 0°F or below for frozen food. Industrial projects must still apply product-specific regulatory, HACCP and customer limits rather than treating these general values as final warehouse design criteria.

Holdover Time Must Be Measured for the Actual Warehouse

Cold-room holdover time cannot be taken from a domestic refrigerator table or a generic industry assumption.

It depends on:

The preferred evidence is temperature-logger data from a previous outage or controlled refrigeration shutdown.

Where measured data is unavailable, the refrigeration engineer should calculate a conservative temperature-rise curve from the room envelope and stored thermal mass.

The engineering submission should include:

BESS, Generator or Thermal Energy Storage?

These technologies perform different functions.

TechnologyMain FunctionMain Limitation
BESSSupplies immediate electrical powerDuration depends on battery capacity
Diesel generatorSupports long electrical outagesRequires startup, fuel and maintenance
Thermal energy storageStores cold for later useDoes not power controls, fans or pumps
BESS plus generatorImmediate response plus long-duration supportRequires coordinated controls
BESS plus thermal storageReduces electrical and cooling demandMore complex system integration

DOE defines thermal energy storage as storing heat or cold for later use. It can discharge stored thermal energy directly for temperature control and reduce electrical demand during peak periods or outages.

BESS and thermal storage are therefore complementary.

A project requiring a hybrid solid-state battery configuration must identify the exact model and project BOM. Chemistry claims should not be transferred from one product family to another.

Cold Storage BESS Sizing Example

Assume a frozen-food warehouse has the following preliminary thermal conditions.

Thermal InputIllustrative Value
Normal frozen-room temperature−18°C
Maximum project operating limit−12°C
Modelled holdover without active refrigeration75 minutes
Required outage protection period2 hours
Selected strategyControls, circulation and one critical compressor

These thermal values are illustrative.

Final sizing requires measured or modelled temperature response for the actual room, product and ambient conditions.

The refrigeration load classification is:

Load GroupIllustrative Power
Controls, sensors and communications15kW
Evaporator fans and refrigerant pumps45kW
One critical compressor circuit120kW
Noncritical compressors and auxiliaries220kW
Total installed refrigeration load400kW
Selected critical backup load180kW

The BESS supports 180kW rather than the complete 400kW plant.

Generator-Bridge Calculation

Assume the generator requires ten minutes to start, synchronize and accept the refrigeration load.

Required AC Energy = 180kW × 10 ÷ 60 = 30kWh

The energy requirement is small, but the PCS must still supply the full critical load.

The PCS must also tolerate:

A 250kW-class PCS may therefore be a more practical preliminary direction than a PCS rated at exactly 180kW.

Two-Hour Backup Calculation

For two hours of critical refrigeration support:

Required AC Energy = 180kW × 2h = 360kWh

Using an illustrative 80% usable SOC window and 90% conversion factor:

Preliminary Nominal Energy = 360kWh ÷ 0.80 ÷ 0.90 = 500kWh

The preliminary direction becomes:

This is an initial engineering range, not a final quotation.

Compressor Starting Must Be Verified Separately

A compressor rated at 120kW may require substantially more than 120kVA during acceleration.

The project must review:

A large battery cannot correct an undersized PCS.

Cold storage EPCs can review the BESS motor-starting engineering guide before selecting converter power.

Prevent Simultaneous Compressor Restart

All compressor circuits should not restart immediately when grid or generator power becomes available.

A controlled recovery sequence is:

The selected energy storage inverter, BMS, EMS, refrigeration controller and generator controller must exchange operating status and power limits.

The detailed signal matrix can follow the BMS and EMS communication architecture guide.

Preliminary MegSolid Product Direction

Cold storage projects should use industrial systems rather than sizing from a Residential Energy Storage product intended for household loads.

The preliminary industrial direction is:

Critical Backup RequirementPreliminary Product Direction
Up to 100kWEvaluate ESSA0100B-0215
Around 125kVAEvaluate 261.24kWh liquid-cooled system
150–250kWEvaluate MEGA0150TS or MEGA0250TS
250–500kWEvaluate MEGA0250TS or MEGA0500TS
500kW–1MW or multi-hour backupEvaluate ESSC containerized BESS
Multiple temperature zonesCompare distributed cabinets and centralized containers

The C&I Energy Storage product category provides the relevant starting point for industrial refrigeration projects.

ESSA0100B-0215

The ESSA0100B-0215 is rated at 100kW AC and 215.04kWh. Its reviewed data identifies LFP cells, a 768V nominal battery and a 0.5C charge/discharge rate at 25°C.

The cabinet uses intelligent air cooling, has an IP54 enclosure and lists an operating range of 0–45°C.

It should be considered only when critical operating and starting requirements remain within the verified system capability.

Higher-Power Configurations

The 261.24kWh system is rated at 125kVA and uses 314Ah LFP cells with liquid cooling. The source lists an operating range of −20–55°C, with derating above 45°C.

MEGA PCS models include 150kW, 250kW and 500kW ratings. The platform lists grid-current THD below 3%, adjustable power factor and automatic on-grid/off-grid operation.

For larger warehouses and cold storage parks, the ESSC series includes 500kW/1.0752MWh and 1MW/2.1504MWh systems.

The Commercial and Industrial Energy Storage architecture should be selected from the verified critical-load profile rather than total installed refrigeration capacity.

Cold Storage BESS Sizing Data Sheet

The first inquiry should request only the data needed for preliminary viability assessment.

Required for Initial Review

Recommended for Detailed Engineering

The resulting engineering response should provide:

FAT and SAT Must Test the Refrigeration Sequence

A steady-state battery discharge test does not prove cold storage backup performance.

The FAT should simulate:

The SAT should verify:

The acceptance scope can reference the BESS Factory Acceptance Testing guide.

Final Procurement Recommendation

A cold storage BESS should be sized from measured thermal risk, critical refrigeration power, compressor starting demand and the required operating duration.

The correct process is:

The objective is not to energize every refrigeration circuit.

It is to keep critical products within their approved temperature range using the smallest reliable MegSolid system that satisfies the verified project conditions.

FAQ

Not necessarily. It should support the minimum compressor, fan, pump and control combination required to maintain the approved product-temperature range.

Yes. Stored products and insulated rooms can slow temperature rise, but the actual holdover period must be measured or calculated.

Yes. PCS power covers the critical electrical load, while battery energy covers the generator starting and synchronization period.

PCS kW and kVA determine how much load can be supplied. Battery kWh determines how long that power can continue.

Only when the critical load remains within 100kW and the verified usable energy covers the required duration.

Potentially. Starting current, starting power factor, acceleration time and PCS overload capability must be verified.

No. Compressors should normally restart in stages to avoid voltage sag, pressure problems and generator or transformer overload.

Not completely. Thermal storage supplies stored cooling, while BESS supplies electricity to controls, pumps, fans and compressors.

Yes, but the EMS must preserve the contracted refrigeration-backup SOC reserve.

Provide temperature zones, product limits, refrigeration loads, compressor starting data, generator information, outage duration and the electrical single-line diagram.

Classify critical refrigeration loads, calculate PCS operating and starting power, define backup duration and adjust nominal battery energy for SOC limits, losses and degradation.

Controls, alarms, refrigerant circulation, evaporator fans and the minimum compressor capacity required to protect product temperature should receive priority.

BESS provides immediate response and short-duration support. Generators are often more practical for long outages. Many warehouses require a coordinated hybrid system.

MegSolid (Hong Kong) Limited focuses on the R&D, design and supply of high-performance energy storage systems. With ten years of technical accumulation, we offer customized outdoor cabinet ESS, residential inverters and portable power solutions for global clients.
WhatsApp/Wechat: +852 59811073

Get Your MegSolid Energy Storage Solution in 24 Hours

Direct from a Solid-State Battery Manufacturer. Receive a customized ESS proposal, ROI analysis, and system recommendation from our engineering team.

What You'll Receive

Trusted Worldwide:

UL, IEC, UN38.3,China Classification Society,GB36276-2023,RoHS

Hot Models:

Applications:

Factories · Solar Farms · Mining · Islands · Data Centers

Tell us your project — we'll design the system for you.

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.