Download Technical Specs PDF

How to Size BESS Backup for Wastewater Lift Stations

A wastewater lift station should not size its BESS from the sum of every installed pump motor.

The design must start with usable wet-well storage, incoming flow, minimum emergency pumping capacity, motor-starting demand and generator response time.

MegSolid separates the requirement into:

The BESS may support PLCs, SCADA, level sensors, alarms, valves and one duty pump. It does not automatically need to energize every standby pump and building load.

Request a Preliminary Pump Station Assessment

Submit the pump schedule, motor-starting method, pump curves, wet-well levels, usable emergency volume, design inflow, generator response time, site voltage and single-line diagram.

The review can return a preliminary PCS range, battery capacity, emergency sequence and missing RFQ data.

Is BESS Suitable for the Station?

EPA recommends assessing the power required by essential infrastructure and key pumping stations rather than classifying every connected load as critical.

Project ConditionBESS SuitabilityDirection
Generator needs 30 seconds to 10 minutesHighBESS bridge
Frequent short outagesHighBattery-led pumping
One duty pump controls inflowHighTiered-load BESS
Pump flow remains below inflowConditionalCalculate net accumulation
Whole plant must run 12–24 hoursLow aloneBESS-generator hybrid
Wet-well storage is unknownCannot sizeHydraulic assessment
Starting demand exceeds PCS capabilityUnsuitable designVFD, soft starter or larger PCS
Station is flood-proneConditionalReview elevation and access

The selected C&I Energy Storage system should support the verified emergency mode, not total connected horsepower.

Use the Four-Layer Sizing Method

LayerEngineering QuestionOutput
Hydraulic riskWhen will the wet well reach its limit?Maximum response time
Critical loadWhich pump and controls must operate?Operating kW
Transient powerWhat happens during pump starting?PCS kW and kVA
Energy durationHow long must loads run?Usable and nominal kWh

Use the commercial energy storage procurement guide to define responsibility for the battery, PCS, EMS, switchgear, protection and commissioning.

Calculate No-Pump Holdover Time

Use only the storage between the selected starting level and maximum permitted level. Exclude sump volume, required pump submergence, sediment allowance and freeboard.

TxDOT guidance similarly separates usable storage from sump and freeboard.

No-Pump Holdover Time = Available Emergency Volume ÷ Incoming Flow

Hydraulic InputValue
Available emergency volume180m³
Outage inflow360m³/h
No-pump holdover30 minutes

This is a response deadline, not automatically the required battery duration.

Calculate Net Flow After the Pump Starts

Once a pump starts, storage accumulation depends on inflow minus active pump flow. Hydraulic design should evaluate inflow and outflow over time.

Net Accumulation Flow = Incoming Flow − Active Pump Flow

With 360m³/h inflow and 270m³/h pump flow:

Net Accumulation = 90m³/h

Time to Maximum Level = 180m³ ÷ 90m³/h = 2 hours

The pump does not fully offset inflow, but it extends the original 30-minute window to two hours.

If verified pump flow equals or exceeds inflow at the actual head, the level should stabilize or fall.

Size Energy From Actual Pump Duty

Assume:

Critical LoadPower
One duty pump90kW
Controls and instruments10kW
Required auxiliaries5kW
Total105kW

Five-Minute Generator Bridge

Required AC Energy = 105kW × 5 ÷ 60 = 8.75kWh

Energy is small, but the PCS must carry 105kW plus the starting transient. A 100kW PCS is already below the continuous requirement.

Two-Hour Continuous-Pump Case

Required AC Energy = 105kW × 2h = 210kWh

At an illustrative 80% usable SOC window and 90% conversion factor:

Nominal Energy = 210kWh ÷ 0.80 ÷ 0.90 ≈ 292kWh

Two-Hour Cyclic-Pump Case

If 15kW of controls runs for two hours and the 90kW pump runs for one hour:

Total AC Energy = (15kW × 2h) + (90kW × 1h) = 120kWh

Nominal Energy = 120kWh ÷ 0.80 ÷ 0.90 ≈ 167kWh

Operating ModelAC EnergyNominal Energy
Continuous pump210kWhAbout 292kWh
50% pump duty120kWhAbout 167kWh

Use the lower value only when the hydraulic model and level-control sequence validate the duty cycle.

Verify Pump Starting Separately

A 90kW motor may require substantially more than 90kVA during acceleration.

Review:

A larger battery cannot correct an undersized PCS.

Review the BESS motor-starting engineering guide and PCS and inverter engineering guide before selecting converter power.

Wastewater pump station wet-well holdover and net accumulation flow calculation guide, illustrating how BESS-powered duty pump operation extends emergency response windows from 30 minutes to 2 hours.

Coordinate the Emergency Sequence

The control hierarchy should follow the BMS and EMS communication architecture.

EPA documents a 1MW battery at a wastewater treatment plant capable of approximately 15 minutes of whole-plant backup before transfer to generators, illustrating the bridge role of storage.

Preliminary MegSolid Product Direction

Critical RequirementPreliminary Direction
Up to 100kWESSA0100B-0215
Around 125kVA261.24kWh liquid-cooled system
150–250kWMEGA0150TS or MEGA0250TS
250–500kWMEGA0250TS or MEGA0500TS
500kW–1MWESSC containerized BESS
Multiple stationsDistributed cabinets or centralized system

Projects within 100kW can evaluate the ESSA outdoor cabinet energy storage system.

The ESSA0100B-0215 is rated at 100kW/215.04kWh and uses intelligent air cooling with IP54 protection.

Review the 215kWh outdoor cabinet ESS guide for model-level context.

Higher-power stations can evaluate the MEGA power conversion system, with 150kW/165kVA, 250kW/275kVA and 500kW/550kVA ratings.

Large plants can evaluate the ESSC containerized energy storage system, including 500kW/1.0752MWh and 1MW/2.1504MWh configurations.

Utilities with several sites should compare modular cabinets versus containerized ESS.

Product selection remains subject to starting kVA, usable energy, ambient conditions, flood elevation, cable distance, protection coordination and the approved operating sequence.

FAT and SAT Requirements

FAT should simulate:

SAT should verify starting current, PCS response, pump flow, wet-well control, SCADA alarms, generator transfer and recharge logic.

Use the BESS Factory Acceptance Testing guide to define witnessed pass/fail criteria.

Final Procurement Recommendation

The design must prove that:

Submit the pump schedule, wet-well levels, flow data and single-line diagram through the MegSolid project inquiry page.

FAQ

No. It should support the minimum pumping capacity required to protect the process.

Divide usable emergency storage by incoming flow.

Subtract pump flow from inflow and calculate time from the net accumulation rate.

Yes. Battery energy covers duration; PCS power covers operating and starting demand.

Possibly, but controls, auxiliaries, power factor and starting demand must also fit.

It may reduce starting current, subject to compatibility and harmonic review.

No. It delays the response deadline but does not stop inflow.

Yes, if emergency SOC remains reserved.

Potentially, but cable distance and simultaneous outage risk may favor distributed systems.

Pump curves, motor data, wet-well levels, inflow, emergency volume, generator data and a single-line diagram.

Calculate hydraulic holdover, minimum pump capacity, starting power and energy from the actual duty cycle.

BESS provides immediate response; generators usually provide longer runtime. Critical stations often need both.

Incoming flow, usable emergency volume, active pump flow, starting demand and backup duration.

MegSolid (Hong Kong) Limited focuses on the R&D, design and supply of high-performance energy storage systems. With ten years of technical accumulation, we offer customized outdoor cabinet ESS, residential inverters and portable power solutions for global clients.
WhatsApp/Wechat: +852 59811073

Get Your MegSolid Energy Storage Solution in 24 Hours

Direct from a Solid-State Battery Manufacturer. Receive a customized ESS proposal, ROI analysis, and system recommendation from our engineering team.

What You'll Receive

Trusted Worldwide:

UL, IEC, UN38.3,China Classification Society,GB36276-2023,RoHS

Hot Models:

Applications:

Factories · Solar Farms · Mining · Islands · Data Centers

Tell us your project — we'll design the system for you.