Download Technical Specs PDF

How to Size BESS for Shore Power at the Port of Rotterdam

A Rotterdam terminal may have enough annual electricity for shore power and still lack sufficient capacity during a three-hour berth overlap.

The problem appears when several loads converge behind the same connection:

This is not solved by adding the nameplate ratings of every shore-power connection. The project needs a time-aligned model of vessel demand, terminal load, grid availability and battery recovery.

Rotterdam already operates more than 100 shore-power installations with over 43MW of combined capacity. Its Shore Power Strategy 2025–2035 also acknowledges that grid congestion is complicating deployment in parts of the port and identifies mobile shore power and alternative grid-contract arrangements as potential responses.

For EPC contractors evaluating storage, the commercial question is:

Can a BESS cover the terminal’s coincident shore-power deficit and recover before the next vessel requires energy?

MegSolid uses the berth schedule—not the number of connection points—as the starting point for this calculation.

Why Rotterdam Shore-Power Projects Need a Different Sizing Method

Rotterdam is moving from demonstration projects into large-scale terminal construction.

In January 2026, Rotterdam Shore Power selected ABB for installations at APM Terminals Maasvlakte II, ECT Delta and ECT Euromax. The projects cover eight kilometres of quay, 35 connection points and more than 100MVA of total shore-power capacity.

This scale does not mean every terminal requires a BESS.

Battery storage becomes relevant when one or more of the following conditions apply:

Terminal ConditionBESS Relevance
Grid-import capacity is below coincident vessel demandHigh
Grid reinforcement will arrive after shore-power commissioningHigh
Vessel overlap creates predictable temporary peaksHigh
Mobile shore power is needed at an unserved berthConditional
Terminal load leaves no reliable recharge windowLow until corrected
Shore-power demand remains above the grid limit for most of the dayBESS alone may be unsuitable
Long-duration supply is required without grid accessEvaluate generation or hybrid supply

The Port of Rotterdam has already demonstrated two locally relevant battery roles.

One pilot used a battery to increase the power available from an existing inland-shipping shore-power box. Another used movable battery containers to supply sea-going vessels at an operational terminal where fixed grid infrastructure was limited.

These pilots prove technical feasibility. They do not establish the required MW, MWh or commercial architecture for a deep-sea container terminal.

Build the Berth and Terminal Load Timeline

The most important design input is a time-series schedule showing what happens behind the terminal connection.

For each vessel, record:

The vessel schedule must then be aligned with:

Annual energy consumption cannot replace this model. Two terminals with the same annual MWh may require very different BESS power because their vessels overlap differently.

Submit the Berth Schedule and Grid Capacity

For a project-specific equipment review, provide:

The broader scope should also be checked against the commercial energy storage procurement guide before the battery, PCS, EMS and shore-power converter responsibilities are assigned.

Calculate the Power Available for Shore Supply

The terminal cannot allocate its full grid connection to vessels.

Available Shore-Power Capacity = Grid-Import Limit − Coincident Terminal Load

Assume the following illustrative Rotterdam terminal:

Electrical InputValue
Contracted grid-import limit3.0MW
Coincident terminal operating load1.6MW
Capacity available for vessels1.4MW

The BESS must cover only the demand above 1.4MW, provided the grid-import limit remains firm and terminal load does not increase.

This calculation should use measured interval data rather than a single monthly peak.

Size BESS Power From Vessel Overlap

Assume two vessels connect during the same afternoon:

VesselShore-Power DemandConnection Window
Vessel A1.2MW10:00–16:00
Vessel B1.8MW13:00–18:00

From 10:00 to 13:00, Vessel A requires 1.2MW. The terminal’s available 1.4MW grid capacity can support it without battery discharge.

From 13:00 to 16:00, both vessels require 3.0MW.

Maximum BESS Power = 3.0MW − 1.4MW = 1.6MW

From 16:00 to 18:00, only Vessel B remains:

Remaining BESS Power = 1.8MW − 1.4MW = 0.4MW

A 500kW BESS would therefore fail during the three-hour overlap, even if its battery contained enough energy to support the later 400kW segment.

The preliminary converter direction should exceed the verified 1.6MW deficit and account for:

Higher-power projects may require a pooled MEGA PCS architecture rather than one converter.

Calculate Energy Across the Full Port Call

The battery must cover every interval in which demand exceeds the permitted grid supply.

For the three-hour vessel overlap:

Overlap Energy = 1.6MW × 3h = 4.8MWh

For the final two hours of Vessel B:

Remaining Energy = 0.4MW × 2h = 0.8MWh

Therefore:

Total AC Discharge Requirement = 4.8MWh + 0.8MWh = 5.6MWh

Using an illustrative 80% usable SOC window and 90% discharge-path factor:

Preliminary Nominal Capacity = 5.6MWh ÷ 0.80 ÷ 0.90 ≈ 7.78MWh

Additional reserve may be required for:

This example shows why a 5MWh container may be insufficient even when the maximum power deficit is only 1.6MW.

Verify Recovery Before the Next Vessel Arrives

A BESS that supports the first port call but cannot recover for the next one does not solve the terminal’s capacity problem.

Assume the battery can recharge between 18:00 and 02:00 and the terminal has 800kW of available grid capacity during that period:

Maximum Grid Energy for Recharge = 0.8MW × 8h = 6.4MWh

With an illustrative 90% charging-path factor:

Energy Restored to the Battery ≈ 5.76MWh

This leaves little or no margin after restoring the 5.6MWh discharged during the previous event.

A later vessel, a higher terminal night load or a shortened recovery window would cause progressive SOC depletion.

Possible remedies include:

The EMS should calculate projected end-of-event SOC before accepting the next shore-power commitment.

Fixed BESS or Movable Battery Shore Power?

ArchitectureBest ApplicationProcurement Risk
Fixed grid-connected BESSHigh-use terminal with repeatable berth schedulesGrid approval and civil integration
Movable battery containersTemporary or currently unserved berthsLogistics, connector handling and higher operating cost
Multiple distributed cabinetsSmaller separated berth loadsMore interfaces and maintenance points
Central containerized BESSMW-scale shared terminal demandLarger failure domain and cable infrastructure
BESS-generator hybridLong outages or insufficient recharge capacityFuel, emissions and control complexity

The Rotterdam movable-battery pilot concluded that the concept was technically feasible but expected it to be more expensive than a conventional fixed grid connection. The port identified locations without grid access or affected by grid congestion as more plausible applications.

Terminals comparing these layouts should review modular cabinets versus containerized ESS before fixing cable routes and civil works.

Where Should the BESS Connect?

A port BESS can be integrated at several points:

Behind the Terminal Grid Meter

The BESS supports the terminal AC bus and reduces import at the point of connection.

This is flexible because the battery can support shore power and selected terminal loads. It also requires coordination with terminal protection and the shore-power conversion system.

At the Shore-Power Converter Input

The battery supports a dedicated converter station rather than the complete terminal bus.

This creates a clearer shore-power boundary but may reduce operational flexibility.

Within a Vendor-Specific DC Architecture

A DC-coupled design may reduce conversion stages, but it creates tighter dependence on the shore-power converter supplier, DC voltage range and protection design.

No topology should be selected from battery efficiency alone.

For high-voltage shore connection systems, IEC/IEEE 80005-1 covers shore distribution, shore-to-ship interfaces, transformers, frequency converters, monitoring, interlocking and power management. A certified BESS cabinet does not make the complete shore-connection system compliant.

Preliminary MegSolid Product Direction

Verified RequirementPreliminary Direction
Up to 500kW deficitMEGA PCS with project-specific battery capacity
500kW / approximately 1MWhESSC 500kW/1.0752MWh
1MW / approximately 2MWhESSC 1MW/2.1504MWh
Multi-MW, 5MWh-class block5000INTL 2.7MW/5.0159MWh
7–10MWh terminal projectMultiple containerized blocks
Flexible temporary berthProject-specific movable architecture

The MegSolid containerized energy storage systems include 500kW/1.0752MWh and 1MW/2.1504MWh air-cooled configurations. The 5000INTL platform provides 2.7MW/5.0159MWh with liquid cooling and IP55 protection.

For the illustrative 1.6MW/7.78MWh requirement, preliminary comparison could include:

This is not a final product commitment. The project must verify PCS parallel operation, medium-voltage transformation, marine corrosion requirements, fire separation, grid compliance and shore-power integration.

Review the 5MWh BESS engineering architecture before selecting a large terminal block.

AFIR and FuelEU Do Not Define the BESS Size

AFIR requires qualifying TEN-T maritime ports to provide sufficient shore-side electricity by 31 December 2029 to serve at least 90% of relevant container and passenger-vessel port calls above the specified threshold.

The Rotterdam strategy is therefore driven by a real infrastructure deadline, but AFIR does not specify the battery capacity required at an individual terminal.

The BESS must still be calculated from:

Regulatory coverage should not be converted into unsupported claims that a battery product is “AFIR certified.”

Rotterdam port shore-power BESS sizing methodology infographic, detailing 3.0 MW combined vessel overlap demand, 1.4 MW available grid capacity, and 1.6 MW active power deficit calculations.

EMS, FAT and SAT Requirements

The port EMS should receive:

The control structure can be developed using the BMS and EMS communication architecture.

FAT should simulate vessel connection, simultaneous berth demand, PCS-block failure, minimum SOC, communication loss, grid-limit violation and controlled shutdown.

SAT should verify actual power at the terminal connection, shore-power converter interaction, harmonic performance, interlocks, emergency stop, recharge logic and recovery before the next scheduled vessel.

Convert these scenarios into witnessed acceptance criteria using the BESS Factory Acceptance Testing guide.

Final Procurement Decision

A Rotterdam port BESS should not be selected from annual shore-power consumption or the total rating of all connection points.

The project is ready for quotation only when it can demonstrate:

Submit the berth schedule, terminal load profile and electrical single-line diagram through the MegSolid project inquiry page.

FAQ

Only when the maximum demand above available grid capacity remains within the verified PCS power and battery duration.

No. It should be sized from the maximum time-aligned vessel demand expected behind the same grid connection.

It identifies when vessels overlap, how long the power deficit continues and when the battery can recharge.

It may defer or reduce an upgrade when the capacity shortage is temporary. A persistent daily deficit may still require reinforcement.

No. Rotterdam’s pilot found it technically feasible but generally more expensive than a fixed connection.

Not with the illustrative reserve and loss assumptions. The preliminary nominal requirement is approximately 7.78MWh.

No. AFIR sets shore-side electricity infrastructure targets, not a mandatory battery architecture.

Yes, when both load profiles are included in the connection-point calculation and the EMS applies clear priorities.

The terminal must reduce shore-power commitments, add generation, increase grid capacity or revise the operating schedule.

Provide berth schedules, vessel demand, terminal interval data, grid and transformer limits, voltage, frequency and the single-line diagram.

Calculate available grid capacity after terminal loads, model coincident vessel demand, integrate every power-deficit interval and verify recharge before the next port call.

It can address temporary and predictable capacity shortages. It cannot sustainably correct a continuous energy deficit without adequate recharge.

High-use terminals generally require a fixed multi-MW containerized system. Temporary or unserved berths may justify movable battery shore power.

MegSolid (Hong Kong) Limited focuses on the R&D, design and supply of high-performance energy storage systems. With ten years of technical accumulation, we offer customized outdoor cabinet ESS, residential inverters and portable power solutions for global clients.
WhatsApp/Wechat: +852 59811073

Get Your MegSolid Energy Storage Solution in 24 Hours

Direct from a Solid-State Battery Manufacturer. Receive a customized ESS proposal, ROI analysis, and system recommendation from our engineering team.

What You'll Receive

Trusted Worldwide:

UL, IEC, UN38.3,China Classification Society,GB36276-2023,RoHS

Hot Models:

Applications:

Factories · Solar Farms · Mining · Islands · Data Centers

Tell us your project — we'll design the system for you.